RESTORATION 2009
January 2009
The smokebox work has been completed with all the superheater elements fitted and the blower pipe work in place. |
The handrails have been fitted and the pipework to carry the electric cabling for the route indicators and AWS is being worked on. |
The delivery pipes to the clack valves have been shaped and fitted. The sandboxes have also been bolted onto the side of the smokebox. Painting is progressing slowly - paint doesn't like cold or damp conditions. | The delivery pipes bolted under the running plate next to the steam heating pipe. The reverser shaft can been seen at the bottom of the picture. |
The controls under the fireman's seat for the Monitor injectors plus the slacker pipe for washing the footplate down. | The vacuum braking system has been tested and, as can be seen from the above photograph, succeeded in creating 20 inches of vacuum on both the train side and chamber side. |
February 2009
The smokebox door has now been fitted and the the paintwork has been rubbed down. The picture above shows the smoke deflectors being trial fitted. | 34059 has been moved to the other road as work was required on the pads for the middle driving wheels, which required the use of the wheel drop. |
Weighing the tender to ensure the weight is evenly distributed over the wheels. | 34059 Sir Archibald Sinclair leaves the workshop and enters the platform at Sheffield Park while tests are carried out on the springs. The motive power was supplied by the 08 Diesel shunter, seen behind the tender. |
Tony Deller the Bulleid Society's technical advisor – and a chartered mechanical engineer – on the footplate of 34059 outside the workshop. | Steve Czech who has overseen the work on Sir Archibald Sinclair |
4th March 2009
SUCCESSFUL STEAM TEST
Tuesday 3rd March 2009 saw a successful boiler insurance test and the following day, Wednesday 4th March, was the first movement of the locomotive under its own steam since withdrawal by BR in May 1966.
The fire viewed through the Ajax doors. |
The pressure is raised successfully to 250lb/sq in. |
Smoke coming from the chimney for the first time since May 1966. | With cylinder cocks open 34059 Sir Archibald Sinclair moves around the yard outside the Sheffield Park woks. |
The locomotive is running with the first 5,250 gallon tender to be built in preservation. The design of this tender, with the twin rear ladders and single rectangular filler, was that which superseded the 5,250 gallon re-bodied tenders in service, but because of the withdrawal of steam were never built. The inset picture shows the rear of 34059's original re-bodied 5,250 gallon tender at Nine Elms, taken on 7th December 1965 by Ken Horan.
The frames for the original BR re-bodied tender (No. 3273) were from a 4,500 gallon version, which was attached to No. 21C123, Blackmoor Vale from 4/2/46 to 22/9/54!
11th March 2009
SUCCESSFUL TEST RUNS
No. 34059, Sir Archibald Sinclair completed two days of test running on Tuesday (10th March) and Wednesday (11th March) which went well.
Tuesday was in reality light engine plus Queen Mary brake van to Horsted Keynes and return.
Wednesday was a loaded test run with five coaches for four runs to Horsted Keynes only, due to an engineering possession to the north, and return. Nothing unforeseen occurred. The final run was light engine to Horsted Keynes for the final painting to be carried out there.
Taking water at Sheffield Park |
Waiting to depart from Sheffield Park. |
On a beautiful spring day No.34059 makes a splendid sight leaving Sheffield Park. | Arrival at Horsted Keynes. |
1st April 2009
No. 34059, Sir Archibald Sinclair in the paint shop at Horsted Keynes. The painting phase is now finished on and the lining out and transfer application is about to commence.
Inside the paint shop at Horsted Keynes. | Back of the tender. |
5th April 2009
Lining and transfers applied to the tender and cab sides. | The left hand cab side. The yellow triangle shows that the BR briquette system of water softening is fitted. |
6th April 2009
No. 34059, Sir Archibald Sinclair was pulled out of the paint shop on Monday, it was then lit up at taken back to Sheffield Park in preparation for more loaded test runs.
No. 34059 basking in the spring sunshine. | No. 34059 after being pulled out of the paint shop, with Maunsell U class No. 1638 arriving with the service train from Sheffield Park. |
7th April 2009
Tuesday (7th April) No. 34059, Sir Archibald Sinclair made trial runs with the Golden Arrow set of Pullmans between Sheffield Park and Kingscote.
The tender carries incorrect 'right facing' lion totems. These had been in store for a long time and inquires are being made into where they came from. Two new totems have been ordered to sort out the problem.
The engine will now re-enter the works at Sheffield Park for 'last minute' work to be carried out.
Awaiting to depart at Sheffield Park | Running around at Kingscote. |
19th April 2009
No. 34059, Sir Archibald Sinclair has been back in the works at Sheffield Park to have the final work carried out, including the fitting of the AWS battery box and the lights above the buffer beam. The boiler will then be washed out and lighting-up commenced to make it ready for the special trains this week.
The tender totems have now been replaced with the correct facing ones.
The newly fitted Smiths speedometer drive. | The smoke deflectors plus nameplate and crest in place. |
The smokebox number and shed plate for Salisbury in place. | The left hand side nameplate and crest. |
For reports on the following click on the text below or the buttons on the left.